Question No : 8 

You are a project manager for an organization that uses Microsoft PPM.
You plan each project in phases. Team members must only see the assignments from a selected phase.
All reports and project schedule views must reflect the entire project schedule, so the entire project is visible to the management team. You need to configure Microsoft PPM.

What should you do?

A. Set the Publish field to No for all tasks that need the assignments to be hidden from the team
members.
B. Delete the assignments that are not ready to be published to the team members.
C. Set up a new security category for the management team.
D. Set the booking type to Proposed tor all tasks that need the assignments to be hidden from the
team members

Answer: A