Question No : 5

A company is using Microsoft PPM to track task progress, The company implements standard overtime and non-billable time tracking. You observe that you cannot enter overtime hours in your current timesheet. You need to ensure that you can enter overtime hours.

What should you do?

A. In your timesheet add Overtime, and then enter the overtime hours,
B. In your timesheet switch to the My Work view, and then enter the overtime hours.
C. In your timesheet add Non-Billable, and then enter the overtime hours.
D. Ask your project administrator to increase Maximum Hours per Day.
E. In your timesheet add the overtime hours to your regular hours.