Question No : 7

An organization uses Microsoft PPM to manage projects. The organization tracks all projects by collecting time on tasks on a daily basis. You need to ensure that resources can enter their time on tasks.Which three actions should you take? Each correct answer presents part of the solution.

A. On the Task Settings and Display page, set the tracking method to Hours of work done per period
B. On the Task Settings and Display page, select Resources should report their hours worked per day
C. On the Task Settings and Display page, clear the check box Force project managers to use the progress reporting method specified above for all projects.
D. On the Task Settings and Display page, select the check box Force project managers to use the progress reporting method specified above for all projects.
E. Instruct the project managers to select the tracking method for their project in Microsoft PPM.


Answer: A,C,D