Question No :1
You are a project manager in an organization that is using Microsoft PPM. You are
managing a 12-month project. Resources have been working on the project for six months.
You need to determine how the project is tracking against the initial goals in terms of
duration, work and cost.
Which three actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area, and arrange them in the correct order.
Answer:
Explanation:
References:
https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan7E775482-AC84-4F4A-BBD0-592F9AC91953